Drawdown starts at Lake J for silt removal
Water levels at Lake Junaluska are falling following the start of a drawdown to dredge silt and litter — and make repairs to infrastructure.
The process, which began this week, will take seven to eight weeks to complete. The exact timeframe is dependent on the amount of rain and snow the area receives over the next couple of months. The drawdown is scheduled for completion by Good Friday, ensuring the lake will be filled for Lake Junaluska Assembly’s annual Easter activities.
The drawdown’s primary purpose is to get rid of the sediment that is deposited into Lake Junaluska from upstream.
“From the very beginning, over 100 years ago, sediment has been deposited in the lake and has to be removed every few years,” said Lake Junaluska Executive Director Jack Ewing. “The lake is one of the greatest assets of Haywood County, and it is important for it to be maintained for its beauty and recreational value.”
While the dam will be open, water from Richland Creek will continue to flow through the lake bed, allowing fish, ducks and other wildlife to remain in the shallow water.
“While wildlife become concentrated during a drawdown, we are told by experts that there are no ill effects on them,” Ewing said. “In fact, people who fish say that the fishing is just as good after the lake comes back up as it was before the drawdown.”
The walking path will remain open, though pedestrians should watch for heavy equipment. However, no boating will be allowed until the lake is restored to a full pool.